Mijas Town Hall’s Contracting Committee has awarded the contract to Siderúrgica Ronda SL to carry out repairs on the roof of the Las Lagunas swimming pool, which has been closed to the public due to defects after twenty years without proper maintenance, the last inspection having been carried out in 2005, according to the council. The budget for the works amounts to 1,031,852 euros.
The project involves work on the entire roof of the sports complex, namely the swimming pool roof (1,256 square metres), the courts area (2,023 square metres) and the administrative area (149 square metres), totalling 3,528 square metres. Although the overall completion period is six months, work will begin on the swimming pool so that it can be reopened to the public as soon as possible.
Inspections carried out ahead of this project revealed significant deterioration in various components of the roof, including auxiliary structural elements, sandwich panels, waterproofing systems and drainage systems.
These deficiencies, as set out in the project commissioned by the Infrastructure Department and drawn up by Ingesa Ingeniería y Diseño SL, compromised the safety, watertightness and durability of the structure as a whole. Among other issues, rusted bolts, deterioration of the roof, gutters and downpipes, and problems with the insulation were identified.
Planned works
Consequently, the entire structural framework will be inspected and renovated, after which sandwich roof panels will be installed. These interventions will be carried out on a localised basis, preserving components in good condition and ensuring the structural continuity of the existing system.
Once the structural works have been completed and the new roof has been properly installed, the rainwater drainage system will be renewed. This will involve the installation of new gutters, downpipes and custom fittings.
Subsequently, the installations will undergo watertightness and operational tests, with the primary aim of verifying that the entire system meets the design specifications and that there are no leaks or areas of water pooling.
Overall, the solution adopted provides a comprehensive and coherent response to the building’s needs, enhancing its safety, functionality and service life, while significantly reducing the risks associated with leaks, corrosion and system failures.